Building a House in the PI for the complete Idiot

Work Flow Chart of Subcontractors over the 22 Week period

Remember that all your hopes and dreams of building a house are going to be executed by a guy like this, so plan for mistakes:

 

Week of Construction (work being performed and number of workers) Cement/Construction Workers Welders Plumber

Plumber and normally 1 or 2 helpers, on call thru project

Electrician 

and helper, on call throughout the project

Painters Tile Layers Ceiling Installers Carpenters for Cabinets Roof Bugman

Worked on call throughout the project

1

13-19 Jan

7 building forms for columns, bending rebar and building columns                  
2

20-26 Jan

5 same as above plus clearing lot                  
3

27 Jan-2 Feb

10 clearing lot digging putting in perimeter wall                  
4

3-9 Feb

10 digging trenches and footings for columns, rebar fabricated for footings   Works on drain pipes              
5

10-16 Feb

16

Columns installed, Coco lumber installed for second floor cement pouring support

    Works on second floor electrical conduits            
6

17-23 Feb

17

Final supports put in place, building permit obtained from the city

    Temporary electric turned on, all conduits installed before cement pour            
7

24 Feb-1 Mar

16

Poured second floor slab only a 3 day work week while cement curing, continued later putting up cement blocks

                 
8

2-8 Mar

17

Blocks for second floor walls worked on. Steel for roof painted

                 
9

9-15 Mar

16

Finished beams second floor, March 12 trusses started getting welded

 

3

Welders start work on roof

               
10

16-19 Mar (short week holy week)

14

First floor internal walls constructed

3

welding trusses and alike for roof

Water pipes being installed              
11

23-29 Mar

14

Smoothing of cement walls downstairs

3

welding trusses and alike roof

Pipes being installed              
12

30 Mar-5 April

14

First floor completed, walls smoothed, stairs built

                 
13

6-12 April

Cement workers off monday for holiday, all other workers worked

14 

(Note: foreman finds a better job and walks off) Window holes door frames and archways are worked on. Door jams being installed

    Switches and plugs being installed 3

Start of neutralizing the cement and primer

  4

Start of 1st floor ceiling installation

 

  Roof installed  
14

13-19 April

10

(Start relieving cement construction workers and some leave to join old foreman)

      5

3 regular house painters and 2 ceiling painters

  4

Ceiling installation

 

  Roof installed  
15

20-26 April

Railing for stairs installed, Solar water heater installed

9

Start preparing tubular steel for front fence

 

      5

same as above

     2 man team, Cabinets for kids, walk in closet, kitchen being made    
16

27 April-3 May

Some doors and jams installed

7

(2 more workers fired for walking off to old foreman)

      6

4 house painters and 2 for ceilings

    Cabinets for kids, walk in closet, my office, kitchen being made    
17

4-10 May

7

Work on front wall

    Light fixtures installed 4

house painters

10

Team starts with bathrooms and upstairs tiles

  Cabinets for kids, walk in closet, kitchen being made    
18

11-17 May

Windows and sliding doors installed, ceiling fans installed

 

7

Work on front wall and cement around house

      4

house painters

10

Work 3 days and finish tiles (with some problems) Also granite counters done

       
19

18-24 May

4

Cement workers cut back

      4

house painters

         
20

25-31 May

2

2 of the previous workers did not show up and guard not required with painters living in the house, Work on balcony

      4

house painters

         
21

1-7 June

2

Work on balcony

      3          
22

8-14 June (but short week, finished in 2 days)

2

Finish work on balcony

      3          
                     